Correspondence regarding the proposed Thabametsi Power Station
15 December 2016
- Letter by CER on behalf of Earthlife Africa Johannesburg letter to the National Energy Regulator of South Africa (15 December 2016)
- Annexure A (Affidavit by Makoma Lekalakala dated 14 December 2016)
- Thabametsi Power Company’s response to Earthlife Africa Johannesburg’s objection (9 February 2017)
- CER letter to IPP Office regarding an update on the Thabametsi Power Company (Pty) Ltd and ACWA Power Khanyisa Power Station (FF) (Pty) Ltd Independent Power Producer Projects (6 April 2017)
- Letter to the Department of Environmental Affairs on behalf of Earthlife Africa Johannesburg (13 April 2017)
- Earthliffe Africa’s recommendations for the climate change impact assessment report for the Thabametsi power station (25 May 2016)
- Earthlife Africa’s comments on the scope of work report for the climate change and palaeontological impact assessments for the proposed Thabametsi power station(10 November 2016)
- A summary of the draft climate change and palentological impact assessment reports for the proposed Thabametsi power station (27 January 2017)
- Comments on the draft climate change impact assessment for the proposed Thabametsi power station (27 February 2017)