Objection to application by Thabametsi to the NER for a licence to operate its porposed coal-fired plant
15 December 2016
Objection by Earthlife Africa Johannesburg to the application by Thabametsi Power Company (Pty) Ltd to the National Energy Regulator of South Africa for a licence to operate its proposed coal-fired power plant
- Letter by CER on behalf of Earthlife Africa Johannesburg letter to the National Energy Regulator of South Africa (15 December 2016)
- Annexure A (Affidavit by Makoma Lekalakala dated 14 December 2016)
- Annexure A1
- Annexure A2
- Annexure A3
- Annexure A4
- Annexure A5
- Annexure A6
- Annexure A7
- Annexure A8
- Thabametsi Power Company’s response to Earthlife Africa Johannesbur’s objection (9 February 2017)